Name new Borivali flyover after CDS Bipin Rawat: BJP writes to BMC

Updated on: 14 June,2022 08:03 AM IST  |  Mumbai
A Correspondent |

BJP leaders write to the civic body, asking that the bridge be named after CDS General Bipin Rawat; also demand that Devendra Fadnavis is invited for the inauguration

Name new Borivali flyover after CDS Bipin Rawat: BJP writes to BMC

The east-west flyover in Borivli is ready for inauguration after four years

The Borivli flyover, which took four years for construction and is finally set for inauguration, has met another challenge with the BJP demanding that the bridge be named after CDS General Bipin Rawat. Former corporators from the party handed over a letter to the BMC administration in this regard on Monday. They have also asked that Opposition leader Devendra Fadnavis be invited for the inauguration alongside Chief Minister Uddhav Thackeray.  
 
The Bharatiya Janata Party’s delegation included party leaders from Borivli and Kandivli, along with former group leader Prabhakar Shinde and party spokesperson Bhalchandra Shirsat. The letter, written by local MP Gopal Shetty, was handed over to P Velrasu, additional commissioner of the BMC. 


“The work for this flyover was first recommended and followed up by MP Gopal Shetty.  Now the work of this bridge is completed. Therefore, MP Gopal Shetty has demanded that the bridge be opened immediately for traffic.  In the coming rainy season, this flyover will provide relief to the citizens from traffic congestion,” said Shirsat. 


Velrasu was not available for comment. 


Ganesh Khankar, BJP’s north Mumbai district president, has also written a letter to the civic commissioner over the inauguration. He mentioned that the flyover may be inaugurated on June 16 and if the CM is not coming for the event and the programme is organised at ministerial level, then BJP’s Mumbai president Mangal Prabhat Lodha should be invited. 

The flyover at Kora Kendra connects R M Bhattad Marg to S V Road junction. 

The work started on November 15, 2018, and was expected to be complete within 24 months excluding rainy seasons. The BMC had initially approved R161 crore for it, but the cost increased fourfold to Rs 651 crore due to an extension connecting it to Western Express Highway.

Rs 651cr
Total cost of the flyover project

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!

Register for FREE
to continue reading !

This is not a paywall.
However, your registration helps us understand your preferences better and enables us to provide insightful and credible journalism for all our readers.

Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK